PROJECT OVERVIEW

PASSER LARS provided a full cable repair spread onboard the ASV Pioneer barge, for the CWind ‘Complete Cable Care’ service offering.

PASSER LARS provided the new modular offshore carousel in the 15m, 2000Te variant, combined with loading tower, 10Te spooling tensioner, integrated cable highway, and a 15Te horizonal deck tensioner.

Scope of work involved

  • PROVISION OF 2000TE NEW BUILD CAROUSEL, LOADING TOWER, 10TE SPOOLING TENSIONER, AND 15TE DECK TENSIONER
  • INTERMEDIATE MOBILISATION OF ALL EQUIPMENT AT PORT OF ROTTERDAM, NL
  • FINAL MOBILISATION AND COMMISSIONING AT PORT OF BLYTH, UK
  • EQUIPMENT OPERATORS AND MAINTENANCE TECHNICIANS
  • MOBILISATION, OPERATIONAL, AND ENGINEERING SUPPORT